Methodology to Define the Logistics Plan for Exploratory Well Projects in Remote Locations Based on PMBOK® Management Philosophy*

Written by
Rate this item
(1 Vote)

The need for petroleum-based energy self-sufficiency has led nations to continually seek new discoveries and to maximize hydrocarbon extraction, whether based on optimization and technological improvements in exploration and production processes, or by expanding exploratory horizons to search for hydrocarbons.


The 1950s marked a great increase in exploratory activity and the intensification of sea expeditions, made possible by the emergence of new exploratory techniques. Over the years, a wide variety of marine structures have been developed, including vessels and platforms equipped for drilling. Currently, some of these drilling units operate in water depths greater than 3,000 meters.


New frontiers in deep-water oil exploration have imposed a series of challenges for the oil industry. One of these challenges is to provide a high level of service for offshore platforms and drilling rigs in order to keep them operating 24 hours a day, seven days a week (24/7) in the most cost-effective manner. Thousands of people have to be transported to the platforms as well as food, maintenance parts, equipment, bulk, fuel, water and other fluids. Support boats and helicopters are used to meet such mobilization needs. Drilling operations are expensive and require continuous allocation of equipment, in some situations this allocation could be difficult to foresee.


A complex onshore logistics comprising a network of reliable suppliers, support base, seaports, airports, heliports, associated services, etc., is needed to support offshore operations in remote areas. Currently, most offshore logistics activities are still carried out in a traditional way, breaking or segmenting the logistics chain into "silos" with little synchronization throughout the process.

In order to successfully meet required logistical support needs for offshore exploration well, it is highly recommended to conceive each well as an operations establishment autonomous PROJECT, in which a Well Project Logistics Plan is carefully designed, with integrated planning and management of all areas involved.


The suggested approach allows for a paradigm shift, merging the concepts of integrated operations and supply chain practices, while applying the Well Delivery Process to improve project performance. The well delivery process execution-flowchart accounts for FEL methodology which provides the means for organizations to develop plans and oversee operations by reviewing the information furnished by project technical teams and stage-gates for reviewing project planning, where the management team decides whether the project may proceed to a next stage with adequate level of risk and uncertainty.


The proposed methodology is based on the available literature, articles and essays presented at international events of the oil and gas industry that deal with projects executed in remote areas, and on the professional experience of the author. This methodology shall serve as a contribution to the implementation of best practices and the development of governance guidelines & structured project methodology, focused on logistic support to establish exploratory drilling operations.


======================================
* Dissertation - Postgraduate LATO SENSU in Petroleum Engineering, Accent in Well Construction. Brazilian Petroleum Gas and Biofuels Institute. Javier Zambrano. Rio de Janeiro, Brazil.

Read 2328 times Last modified on Monday, 15 April 2019 20:25

Leave a comment

Make sure you enter all the required information, indicated by an asterisk (*). HTML code is not allowed.

7 comments

  • Comment Link Wrubel Wednesday, 30 October 2019 13:39 posted by Wrubel

    I've included this blog post to my favorites

    Report
  • Comment Link Hagin Tuesday, 17 September 2019 12:12 posted by Hagin

    I included this write-up to my bookmarks

    Report
  • Comment Link Capo Tuesday, 17 September 2019 09:08 posted by Capo

    Many thanks sharing this post and rendering it public

    Report
  • Comment Link Javier Zambrano Wednesday, 15 May 2019 22:37 posted by Javier Zambrano

    Dear Mr. Moore:
    Thanks for your comments submitted on April 23, 2019.
    In response to your questions, I would like to let you know that in my role of Procurement and Logistics Coordinator, I have been involved in the implementation of the "Well Delivery Process methodology" to improve project performance for the exploratory campaigns in which I have participated. We have obtained excellent results related with the optimized execution of the projects (time and cost), specially for our exploratory projects in Tanzania, Namibia and Colombia. I can highlight cost reductions between 8% to 15%, Zero Lost Time, Zero Oil Spill Events, Zero injuries, Zero environmental incidents. Based on these previous experiences, we have been incorporating the lessons learned in our operations in the US GoM projects with potential cost savings between 4% and 50% depending on the nature of the services negotiated with vendors.

    Report
  • Comment Link Daniel Moore Tuesday, 23 April 2019 18:32 posted by Daniel Moore

    Hello Javier,

    This is a very interesting article, because I'm currently employed in the Oil & Gas Industry, but never really took much thought into everything it takes to make offshore operations successful, as I am based only in the corporate office. You are right, a well defined and strategic methodology is needed in order to streamline the many inputs that account for such operations. What has been your role and experience as it relates to implementing such methodologies? Are there any specific examples you can share?

    Report
  • Comment Link Mariela Barrueta Tuesday, 16 April 2019 18:44 posted by Mariela Barrueta

    I'm new to this blog and loved this article.

    Report
  • Comment Link Javier Zambrano Tuesday, 16 April 2019 18:38 posted by Javier Zambrano

    Looking forward to your question... Thanks!

    Report